As I metioned, the delivery guy was awesome and since we were about 20 minutes behind, he helped us set everything up for the pours.
These 22 holes were 36 inches wide, 58 inches deep and we put between 10-12 inches of concrete in to make the pad. about 3-4 hours later we were able to set the poles on them.
to get to the west side of the property was quite tight, but he was a great driver and was able to reach 18 out of 22 holes. We wheel barreled the rest.
I called and asked for an extra half yard, bringing my total to 5.5 cubic yards and we ended up being almost a full hole short. Kind of sucked, but we just sent dad to a couple local hardwares to pick up some bag mix. So it took just about 6 yards to finish to complete
|